Project: Early Works
The Early Works phase is progressing for the Guinea Alumina Project. During this phase GAC is progressing long-lead items in preparation for a fast ramp up in construction following project approval.
Early works activities commenced / completed to date include:
- Earthworks and drainage at the refinery site
- Construction of the Kamsar Container Quay
- Piling test work and production piling
- Refinery fencing completion
- Rail spur construction
- Completion of Boké road bridge and handover to the Government of Guinea
- Construction of the first stage construction accommodation camp
- Geotechnical investigations for the freshwater dam and port
- Engineering for the port and refinery facilities
- Geotechnical analysis of the port platform and the freshwater dam site
- Logistics plans and studies
- Baseline environmental monitoring
- Establishment of an Early Works Construction Camp
Community based health, safety, environment, and capacity building activities during Early Works include:
- Community infrastructure development including development of wells, health posts, and schools
- Mentoring and development of local Small and Medium Size Enterprises (SMEs)
- Baseline environmental monitoring
- Support for agricultural and farming programs aimed at improving practices
- Upgrade of facilities and health and safety training of teachers at the Boké Centre de Formation Professionelle – a local technical training college
Early Works activities will transition into the Construction / Project Execution Phase upon Notice To Proceed.